Vindin St. Overhead Pole Line Rehabilitation Project

Vindin St. Overhead Pole Line Rehabilitation Project

Project Timelines

Start DateAnticipated Completion Date
Nov 16, 2026Jan 31, 2027* 

*Weather permitting.

NT Power has retained a third-party contractor, Sturdy Power Lines LTD, to perform a pole line rehabilitation project on Vindin St, Sixth St, and Ontario St. 

Work on this project is scheduled to start on November 16, 2026, with an anticipated completion date of January 31, 2027. Any changes and updates in project timelines will be posted on this page.

About this Project

NT Power is committed to delivering safe and reliable electricity to our customers. As part of that commitment, we will be working to replace aging electric utility infrastructure in the area. These upgrades will improve the reliability and quality of service for all customers in the area.

To complete this work in a safe manner, it has been identified that brief power interruptions will be required. NT Power will provide advance notice to affected customers when the power outage times have been finalized. NT Power will continue to post live updates on its website and social media to enable our customers to track changes to the construction work and scheduled outages.

What To Expect 

  • To complete this work, brief power interruptions will be required, for which you will be notified in advance. If, for any reason, extended outages are required, an extended notification lead time will be given. Every effort will be made to reduce the frequency and duration of outages.
  • Due to the nature of the work, there will be construction-related noise, dust, and lighting from the equipment and trucks, though every effort to minimize this will be made.
  • Access to the roadway will be maintained. Temporary sidewalk closures or pedestrian detours may be in place while the work is underway, with signs in place to direct pedestrians as needed. Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.
  • Every effort will be made to minimize disruptions as much as possible. When the work is complete, any disturbances to property or roadways will be restored to "as good or better" condition. 

For more information, please get in touch with the NT Power Operations Center Monday through Friday, 7:00 a.m. to 3:00 p.m., using the contact details below or through the online form at ntpower.ca/contact.